The launch date planner: a date you can keep
Psychology students predicted they would finish their thesis in 33.9 days and took 55.5; fewer than a third finished by their own predicted date, and fewer than half finished even by their worst-case date. This planner replaces your gut date with one based on how long your past projects really took.
People plan from the best case, even when they know their own history.
Roger Buehler, Dale Griffin and Michael Ross asked 37 honours students to predict when they would hand in their thesis. Average prediction: 33.9 days. Average actual time: 55.5 days. Only 29.7% finished by their predicted date. Asked for a worst case, "if everything went as poorly as it possibly could", they said 48.6 days, and only 48.7% finished by then. In later studies the same team found that people focus on the plan in front of them and ignore how long similar tasks took before. Published in the Journal of Personality and Social Psychology in 1994.
01Break the launch into pieces
List every piece and your best guess in working days. Small pieces are easier to estimate than one big launch.
| Piece | Best guess (days) | Waits on someone else? |
|---|---|---|
| Example: payment and receipts | 2 | Yes: payment provider approval |
02Pieces people forget
Tick the ones that apply and add them to the table.
03Check your own track record
Three past projects of any kind. Divide what it took by what you planned.
| Past project | Planned | Actual | Actual ÷ planned |
|---|---|---|---|
| Example: company website | 3 weeks | 5 weeks | 1.7 |
No history? Start with 1.6. That is the ratio in the thesis study: 55.5 days taken for 33.9 days predicted.
04Run a premortem
Imagine the launch date has passed and you did not ship. Write the story of why.
05Calculate the date
- Add up the piecesTotal working days, including the forgotten pieces you ticked.
- Multiply by your ratioYour average of actual ÷ planned. This is your buffer, taken from your own history.
- Add the waitsReviews, approvals and other people have their own calendar. Add those days on top.
- Convert to the calendarDivide by the working days you really have each week. Count holidays and your day job.
06Publish the new date
A solo founder launching a booking tool, working three days a week on it.
- Gut date
- "Four weeks."
- Pieces
- 11 pieces, 20 working days. The checklist added receipts, password reset and phone testing: 24 days.
- Track record
- Last three projects: 1.7, 1.5 and 2.0. Average 1.7.
- Premortem
- "Payment approval took two weeks." She applies today, not at the end.
- Calculation
- 24 × 1.7 = 41 working days, plus 5 days of waits = 46. At three days a week: 15 weeks.
- Published
- She tells her five pilot customers: launch on the 15th, fifteen weeks from now. First cut if late: the calendar sync.
Write the planned and actual duration of your last three projects. Calculate your ratio.
Describe it. Ship it.
The shortest piece of a launch should be the build. Describe your product and Youmake builds a working version, so your date depends on customers, not on code.
Build your first projectyoumake.devSource: Roger Buehler, Dale Griffin and Michael Ross, "Exploring the 'Planning Fallacy': Why People Underestimate Their Task Completion Times", Journal of Personality and Social Psychology 67(3), 1994, study 1. The premortem is a technique described by psychologist Gary Klein. The planner is our own tool.